Project Updates


Published on August 28, 2019

Welcome to the Facilities Project Updates page.  Below you will find project schedules, impacts, updates, and more!

INITIATIVES

PROJECTS

    Mount Zion Cancer Research Center - Air Intake Design Project
    April 2021-November 2021



    Facilities Services is upgrading the air intake system in the building with the installation of a glass storefront designed to reduce exhaust, dirt, and debris drawn from the street. The glass wall will also help to maintain light levels of the conference rooms located there while reducing costs to building maintenance.

    This project will occur in two phases with the first phase on Sutter Street scheduled to begin on Friday, April 30 and is expected to be complete by Wednesday, August 11. The second phase on Bush Street side will immediately follow and is expected to complete by November 24, 2021.All work will be performed on the exterior of the building or in the basement level below the air intake system. In order to minimize impact to occupants, work that is noisy and requires electrical or HVAC system shutdowns will be performed on Fridays and Saturdays, when possible. See below for the noise impact schedule.

    Phase 1 - Sutter Street (April 30 - August 11)

    Dates of Scheduled Work

    Activity

    Impact

    4/30 - 5/5


    Construct temporary wall near front entrance

    Activity and contractors near main entrance

    5/5 - 5/6

    Demolition of exterior grates

    Minor construction noise and activity outside conference room

    5/7 - 5/11

    Demolition of Duct Silencers

    Air on Sutter side will be shut down. Consistent, loud cutting and grinding noise

    5/11 - 5/13

    Electrical work and field measuring

    Minor construction noise

    6/8 - 6/24

    Exterior Steel installation

    Intermittent Drilling of Concrete

    6/24 - 7/1

    Reinstall insulation

    Intermittent loud pops from powder-actuated tools

    7/1 - 7/6

    New exterior light installation

    Minor construction noise

    7/6 - 7/8

    Reinstall exterior grates

    Typical Construction noise and activity outside of 1st floor conference room

    7/8 - 7/24

    Install storefront windows

    Typical construction noise and activity outside of 1st floor conference room

    7/24 - 8/10

    Inspections and cleanup

    Activity outside 1st floor conference room

    8/10 - 8/11

    Demo temporary Wall

    Activity and contractors near main entrance

    Phase 2 - Bush Street (August 2021 - November 2021)

    Exact dates TBD depending on work progress of Phase 1.

    Questions about this project can be directed to:
    Lee Ann Depew, Infrastructure Programs/NOVA Partners | .(JavaScript must be enabled to view this email address)
    Jeffery Mills, Facilities Manager | .(JavaScript must be enabled to view this email address)

    ***

    Inclusive Restroom Project
    December 2019 - Expected 2022

    Phase 1 - Convert Existing Facilities (Complete)

    Identify and convert single-occupancy or single stall restrooms to inclusive restrooms. This scope is limited to changing signage and locksets on the doors.

    Phase 2 - Renovation and Addition of New Restrooms (In Progress)

    Identify buildings that do not have any single stall restrooms and either add a new inclusive restroom or renovate existing restrooms to inclusive restrooms.

    The following restrooms were completed under Phase 1:

    Click on image to enlarge map

           
    Address

    Building Name

    Floor / RR #

    513 Parnassus Ave. Health Sciences West (HSW) Floor 6, Room 6T3
    513 Parnassus Ave. Health Sciences West (HSW) Floor 13, Room 13T3
    513 Parnassus Ave. Health Sciences West (HSW) Floor 16, Room 16T3
    2 Koret Way School of Nursing (SON) Floor 5, Room 5T2


    Click on image to enlarge map

                   
    Address

    Building Name

    Floor / RR #

    600 16th Street Genentech Hall Floor 1, Room N1T4
    600 16th Street Genentech Hall Floor 1, Room N1T5
    600 16th Street Genentech Hall Floor 1, Room S1T3
    600 16th Street Genentech Hall Floor 1, Room N163
    600 16th Street Genentech Hall Floor 1, Room N155
    600 16th Street Genentech Hall Floor 1, Room N155
    1855 Folsom Street Mission Center Building (MCB) Floor 1, Room 1T3
    1855 Folsom Street Mission Center Building (MCB) Floor 1, Room 1T4


    Click on image to enlarge map

       
    Address

    Building Name

    Floor / RR #

    2340 Sutter Street Cancer Research Center Basement Floor, Room 0T1
    2340 Sutter Street Cancer Research Center Basement Floor, Room 0T2

    Questions about this project can be directed to:
    Geetanjali Ningappa, Infrastructure Programs/NOVA Partners | .(JavaScript must be enabled to view this email address)
    Melissa Cherry, Renewal Program Manager | .(JavaScript must be enabled to view this email address)

     

SHUTDOWN IMPACTS